Our Facility Timeline


May 2023
Lease Signed

May 2023
Lease Signed

June 2023
Letter of Support
November 2023
Demolition Started


December 2023
Demolition Continues


January 2023
Demolition Continues

February 2024
Demolition Finished


February 2024
Demolition Finished


April 2024
Trenching Started
April 2024
Trenching Started


July 2024
Building Permit Acquired & Construction Started


August 2024
Framing Walls Up


September 2024
Sheetrock Installation

October 2024
Sheetrock Installation
October 2024
Insulation


December 2024
FRP Installation in Grow Rooms.
December 2024
FRP Installation in Grow Rooms.


January 2025
FRP Installed, Machinery Goes Up
January 2025
Power Upgrade


January 2025
Power Upgrade


February 2025
Lights Go Up


February 2025
Floors Poured


March 2025
Benches Being Installed


March 2025
Fertigation Room


March 2025
Bakery